Project Timeline

Implementation Plan

A comprehensive roadmap for bringing the Oakland Park Convention & Workforce Innovation Center from concept to reality through structured phases and measurable milestones

Project Phases

The project follows a structured three-phase approach from planning through launch

Phase 1
6-9 months

Planning & Pre-Development

Ready to Begin

Key Milestones

  • Property transition/lease agreements

    2-3 months

  • Zoning and permitting approvals

    3-4 months

  • Federal/state grant applications

    2-3 months

  • Finalize architectural plans

    2-3 months

  • Secure financing commitments

    2-3 months

Expected Deliverables

  • Approved site plans and permits
  • Secured project financing
  • Federal/state grant commitments
  • Final architectural designs
  • Contractor selection
Phase 2
18-24 months

Construction & Development

Scheduled

Key Milestones

  • Site preparation and infrastructure

    3-4 months

  • Convention center construction

    12-15 months

  • Business suites and residential units

    10-12 months

  • Food court and retail spaces

    8-10 months

  • Youth Innovation Hub setup

    4-6 months

Expected Deliverables

  • 30,000 sq ft convention center
  • 30-40 business suites
  • 40 residential live-work units
  • Food courts and retail spaces
  • Youth programs facilities
Phase 3
3-6 months

Launch & Operations

Future

Key Milestones

  • Staff recruitment and training

    2-3 months

  • Tenant/vendor selection

    2-3 months

  • Marketing and pre-booking campaigns

    3 months

  • Grand opening events

    1 month

  • Community program rollout

    2 months

Expected Deliverables

  • Fully staffed operations team
  • Occupied business and residential units
  • Active food court vendors
  • Booked convention events
  • Launched youth programs

Implementation Activities

Critical activities organized by category to ensure successful project delivery

Site Development

  • Property acquisition/lease finalization
  • Environmental assessments
  • Site clearing and preparation
  • Utility infrastructure upgrades
  • Parking and access improvements

Regulatory & Compliance

  • Zoning variance approvals
  • Building permits acquisition
  • Environmental compliance
  • Safety and accessibility certifications
  • Business licensing

Financial & Legal

  • Grant application submissions
  • Private equity closing
  • City/CRA agreements
  • Insurance and bonding
  • Partnership agreements

Community Engagement

  • Public information sessions
  • Local hiring initiatives
  • Vendor selection processes
  • Youth program partnerships
  • Stakeholder communication
Key Partners

Project Stakeholders

Collaborative partnership bringing together expertise from multiple sectors

Developer

Jack Cannon

Private equity investment and project development

Management

FV & Associates

Operations, management, and community programs

City Partner

City of Oakland Park

Zoning support, infrastructure, grant sponsorship

Workforce Partner

CareerSource Broward

Job training and workforce development programs

Financial Planning

Investment & Funding Timeline

Strategic funding deployment across project phases ensures efficient capital utilization and minimizes financial risk

Phase 1 Investment

Planning & Pre-Development

$2-3M

Phase 2 Investment

Construction & Development

$14-15M

Phase 3 Investment

Launch & Operations

$1-2M

Total Phase 1 Investment

Complete project funding

$18M

Contact Project Team

Get involved or learn more about implementation

Developer

Jack Cannon

Private Development Lead

Management & Operations

FV & Associates

Project Contact

Ferlindo Vincent

[email protected]

785-410-7751

Ready to Move Forward?

Let's discuss the next steps and how this project will transform Oakland Park